Noticias electrónicas de Foothill Gold Line
November 2023
November was another good month on the 9.1-mile, four-station Glendora to Pomona project. The four new light rail stations continue to take shape, as work is getting underway on the associated parking facilities. Miles of overhead and underground wires and cables for the light rail power and train control systems continue to be installed; and crews are returning to various grade crossings to complete roadway and safety improvements. Meanwhile, each station’s dedicated artist/artist team remain busy working with fabricators to bring their station artwork to fruition.
Simultaneously, the Construction Authority is readying the 3.2-mile, two-station Pomona to Montclair project segment for a design-build procurement. Metro is expected to submit the project for full funding through SB125 by the end of 2023; and the Construction Authority plans to begin the 15-month process in early 2025 to hire a design-build team for the final project segment.
Continúe leyendo para obtener más información sobre las actividades de construcción actuales.
|
Below are status updates on the various elements that make up the new light rail stations, including the platform canopies, decorative elements, communications and power systems, parking facilities, and station art. All four stations will be center platform stations, with a track on each side – one for westbound trains, and one for eastbound trains – and each station’s parking facility will feature amenities for riders arriving by bike, walking, bus and drop-off.
Photos: Crews completing installation of diamond-shaped shingles atop boarding canopy (top) and glass panels atop TVM canopies (middle) at future Glendora station; (bottom) View of station with completed canopy roof elements
Crews recently completed installation of the decorative roof elements atop the canopy structures at the future Glendora station. As seen in the photos above, crews installed diamond-shaped shingles at the boarding canopy and glass panels with citrus-inspired patterns at the ticket vending machine (TVM) canopies to the west and east. These same decorative elements will be used at each of the four new stations.
Photo: Crews installing overhead catenary system pole at future Glendora station
Earlier this week, crews began installing the final set of overhead catenary system (OCS) poles for the station area, as seen in the photo above. Crews will later install the overhead wires across these poles to provide power for the future light rail trains.
Foto de : Future Glendora Station
Justo al sur de la plataforma de la estación, las cuadrillas casi han despejado todo el sitio del futuro estacionamiento de la estación antes de su construcción (ver foto arriba). El sitio se ha utilizado durante muchos meses como área de depósito de materiales del proyecto.
Photo: Crews installing overhead wires at the future San Dimas station
At the future San Dimas station, crews recently installed the overhead wires that will provide power to the future light rail trains, as seen in the photo above.
Photos: Crews installing decorative glass panels atop TVM canopy at future San Dimas station
Shortly after, the same specialized crew that installed the glass panels at the Glendora station began carrying out the same work at the future San Dimas station, as seen in the photos above. The San Dimas station has just one TVM canopy, located at the west end of the station platform by San Dimas Ave., and crews are already nearing completion on the glass panel installation.
Photo: Crews installing metal roof atop board canopy at future San Dimas station
Earlier this week, crews began installing the metal roof layer atop the boarding canopy (shown above). Once the full metal roof layer is installed, crews will install the diamond-shaped decorative shingles.
Foto de : Sitio del futuro estacionamiento de la estación San Dimas
Across the street and west of the future station, crews have recently completed the demolition and clearing of the former San Dimas Park & Ride lot, which will serve as the site of the San Dimas station parking facility (see photo above).
Photos: (top) Future La Verne station under construction; Crews fabricating canopy columns (middle) and braces (bottom) to be installed at future La Verne station
With most of the platform completed at the future La Verne station, crews are getting ready to install the canopy structures onto the platform. At an off-site location, crews are currently fabricating the canopy parts that will soon be delivered for installation, starting first with the columns and braces (the pieces that provide additional support for the roof), as seen in the photos above.
Fotos: En marcha la construcción del futuro aparcamiento de la estación de La Verne
Just south of the future La Verne station platform, construction continues on the station parking facility. As seen in the photos above, crews are currently carrying out underground utility work throughout the site. This is the first of the four parking facilities to be underway with major construction.
Photos: (top) La Verne station artist Blue McRight and Foothill Gold Line staff meeting with fabricator; (bottom) Sample rendering of future La Verne station artwork
In addition, the same fabricator making the canopy structures will soon begin work on the La Verne station art pieces. As seen in the photo above, La Verne station artist Blue McRight recently held a meeting with the fabricator ahead of crews beginning the fabrication work on three 8-foot-tall art sculptures that will pay homage to La Verne’s history and architecture, as well as the community’s connection to water and agriculture (see drawing above).
Photos: (top) Future Pomona station under construction; (bottom) Crews reconstructing the center section of the Metrolink parking lot between the future Pomona light rail station and Pomona North Metrolink station
Just south of the future Pomona station, crews continue to rebuild the existing parking area for the Pomona North Metrolink station. Late last month, crews completed the necessary work at the east section of the parking lot to allow it to reopen for use. Crews have fully closed and are now rebuilding the center section of the parking lot (see photo above) through Jan. 15, 2024, temporarily eliminating vehicle thru traffic and creating two temporary parking areas (one on the east side of the closed section and one on the west side). For information on this closure and work, haga clic aquí.
To learn more about the plans for the future stations, including the station artwork, see these fact sheets: Glendora, San Dimas, La Verney Pomona.
|
With major work on the light rail track system complete, crews continue to install miles of overhead and underground wires and cables for the light rail power and train control systems. Each system is being constructed by separate, specialized crews that coordinate extensively with one another.
Photos: Crews installing overhead wires across the OCS poles atop the Bonita Ave./Cataract Ave. light rail bridge in San Dimas
As seen above in the Glendora station section, crews are now installing the final sets of overhead catenary system (OCS) poles for the project. Nearly all of the 350 OCS poles needed for the project are now installed, with most of the remaining poles set to be installed soon through the Pomona station area.
Throughout stretches of the corridor where the poles are fully installed, crews continue to install the overhead wires across the poles, as seen in the photos above. The overhead wires will provide power to the light rail trains when the train’s pantograph comes into contact with the wire (light rail trains run on electricity).
Photos: Crews installing underground cables for light rail system in La Verne
Crews also continue to install miles of underground cables for the power, train control and communications systems (see photo above).
|
Photo: Crews conducting finishing work on the retaining walls of the Lone Hill Ave. light rail bridge approach in Glendora
Crews are nearing completion on applying a dry finish onto the miles of decorative retaining walls that are now installed throughout the project. Some of these retaining walls are fairly large, like the one seen in the photo above at the Lone Hill Ave. light rail bridge in Glendora, and comprised of hundreds of individual concrete panels that feature citrus-inspired patterns designed by Alignment artist Christie Beniston.
|
A lo largo del proyecto, las cuadrillas están regresando a varios cruces a nivel para completar el trabajo restante en las carreteras, aceras y mejoras de seguridad.
In Glendora, crews continue to implement intermittent lane closures on Route 66 between Hunters Trail and Compromise Line Rd. (haga clic aquí para el aviso) through the end of the year to complete work on the roadway, sidewalks and bridges.
Photo: Crews working on crossing safety upgrades at the E St. crossing in La Verne
In La Verne, crews are continuing crossing safety upgrades at various crossings (see photo above at E St.).
|
Para ver más de estas y otras actividades que tuvieron lugar el mes pasado, haga clic aquí o debajo para ver el último video destacado del proyecto.
|
La Autoridad de Construcción actualmente busca $798 millones para completar el segmento del proyecto de 3.2 millas desde Pomona a Montclair que incluye las dos últimas estaciones del programa Foothill Gold Line de 25 estaciones. La agencia espera que Metro presente la solicitud de financiación completa a CalSTA a finales de este año. CalSTA es la agencia estatal que supervisa la asignación de $4 mil millones en todo el estado de fondos SB125 aprobados como parte del presupuesto estatal 2023-24; Se espera que $1 mil millones de dólares lleguen al condado de Los Ángeles.
In anticipation of this future funding, the Construction Authority is preparing the Pomona to Montclair project segment for a design-build procurement. El proceso de adquisición de 15 meses comenzará en enero de 2024. Una vez que se obtenga la financiación y se contrate a un contratista, el proyecto tardará cinco años en construirse en Claremont y Montclair.
To stay updated on the upcoming Pomona to Montclair design-build and other procurements, haga clic aquí to sign up for Contracting Opportunities Updates.
|
Gracias por su continuo interés en Foothill Gold Line. Agradecemos su paciencia mientras construimos este importante proyecto regional.
Lisa Levy Buch, Oficial Principal de Comunicaciones y Desarrollo Estratégico y el Equipo de Asuntos Públicos
¡Tómese un minuto para registrarse para recibir actualizaciones importantes y el boletín electrónico mensual de la Autoridad de Construcción!
Después de enviar su dirección de correo electrónico mediante el formulario a continuación, se le pedirá que seleccione las actualizaciones específicas que desea recibir de la Autoridad de Construcción, así como que proporcione información adicional como su nombre y ciudad.
Pomona a Montclair Design-Build y otras adquisiciones futuras
Regístrese para ser agregado a la lista de correo de Oportunidades de Contratación: