THE COUNTDOWN HAS BEGUN

233 days 14 hours
# of Days/Hours to Construction Completion

Construction Activity Maps

Click on the maps below to view construction activities, lane and road closures, detour routes and more.

Pasadena to Arcadia, Arcadia, MonroviaDuarte, IrwindaleAzusa Downtown, and APU/Citrus College.


Pasadena to Arcadia

Arcadia

Monrovia

Duarte

Irwindale

Azusa Downtown

APU/Citrus College

Construction Updates

Construction is under way on the Foothill Gold Line from Pasadena to Azusa and is scheduled to be completed in September 2015, when it will be turned over to Metro for testing and pre-revenue service. Please click here to learn about the Foothill Gold Line from Pasadena to Azusa.

Claims: For information on how to submit a claim, click here.

Latest construction notices (scroll down or click on your city link below):

Pasadena   Arcadia   Monrovia   Duarte
Irwindale   Azusa   Glendora   Gold Line Bridge

Pasadena to Azusa Alignment Project Construction Notices

Pasadena to Azusa Alignment Project Community Hotline: 626-324-7098

Pasadena

 

February 2015 thru Summer 2015

Train Testing & Extended Work Hours

Train testing has started and will take place throughout the cities of Pasadena, Arcadia, Monrovia, Duarte, Irwindale and Azusa over the next several months. As a result, some construction activities will need to be done during a second shift when trains are not occupying the tracks. Second shifts will be necessary periodically and will take place throughout the corridor. Second shifts will start at 3:30 PM and conclude by 9:00 PM.

Letter to Our Neighbors Regarding Train Testing and Extended Work Hours


Arcadia

 

February 2015 thru Summer 2015

Train Testing & Extended Work Hours

Train testing has started and will take place throughout the cities of Pasadena, Arcadia, Monrovia, Duarte, Irwindale and Azusa over the next several months. As a result, some construction activities will need to be done during a second shift when trains are not occupying the tracks. Second shifts will be necessary periodically and will take place throughout the corridor. Second shifts will start at 3:30 PM and conclude by 9:00 PM.

Letter to Our Neighbors Regarding Train Testing and Extended Work Hours

Sept. 17, 2013 - Spring 2015

Construction of Arcadia station parking facility taking place between Santa Clara St and St. Joseph St.


Monrovia

 

February 2015 thru Summer 2015

Train Testing & Extended Work Hours

Train testing has started and will take place throughout the cities of Pasadena, Arcadia, Monrovia, Duarte, Irwindale and Azusa over the next several months. As a result, some construction activities will need to be done during a second shift when trains are not occupying the tracks. Second shifts will be necessary periodically and will take place throughout the corridor. Second shifts will start at 3:30 PM and conclude by 9:00 PM.

Letter to Our Neighbors Regarding Train Testing and Extended Work Hours

Jan. 19 - 23, 2015

City of Monrovia will be constructing off-site improvements on the following streets: Myrtle Ave, California Ave, Duarte Ave, Pomona Ave, Magnolia Ave, and Primose Ave. On-site improvements will also take place at the Monrovia Park and Ride lot. Beginning January 17, 2015 thru May 2015, the Park and Ride lot will be closed.

Mid-Oct. 2013 - Mar. 2015

Construction of Monrovia station parking facility taking place west of Primrose Ave and south of Pomona Ave.


Duarte

 

February 2015 thru Summer 2015

Train Testing & Extended Work Hours

Train testing has started and will take place throughout the cities of Pasadena, Arcadia, Monrovia, Duarte, Irwindale and Azusa over the next several months. As a result, some construction activities will need to be done during a second shift when trains are not occupying the tracks. Second shifts will be necessary periodically and will take place throughout the corridor. Second shifts will start at 3:30 PM and conclude by 9:00 PM.

Letter to Our Neighbors Regarding Train Testing and Extended Work Hours


Irwindale

 

February 2015 thru Summer 2015

Train Testing & Extended Work Hours

Train testing has started and will take place throughout the cities of Pasadena, Arcadia, Monrovia, Duarte, Irwindale and Azusa over the next several months. As a result, some construction activities will need to be done during a second shift when trains are not occupying the tracks. Second shifts will be necessary periodically and will take place throughout the corridor. Second shifts will start at 3:30 PM and conclude by 9:00 PM.

Letter to Our Neighbors Regarding Train Testing and Extended Work Hours

Beginning December 2013

Frontage road west of North Irwindale Ave closed to thru-traffic for Irwindale Station parking construction.


Azusa

 

February 2015 thru Summer 2015

Train Testing & Extended Work Hours

Train testing has started and will take place throughout the cities of Pasadena, Arcadia, Monrovia, Duarte, Irwindale and Azusa over the next several months. As a result, some construction activities will need to be done during a second shift when trains are not occupying the tracks. Second shifts will be necessary periodically and will take place throughout the corridor. Second shifts will start at 3:30 PM and conclude by 9:00 PM.

Letter to Our Neighbors Regarding Train Testing and Extended Work Hours

Nov. 2013 - Jun. 2015

Construction of APU/Citrus College station parking facility taking place west of the future extension of Citrus Avenue, north of Foothill Boulevard.


Glendora

 

 

No construction notices at this time


Archives


Gold Line Bridge Construction Notices

*Construction on the Gold Line Bridge was completed in December 2012.

Archives